Introduction
An OEM working in eastern Germany was looking for an external service provider who could handle overall project management in the construction phase for building a new paintshop for bodies-in-white. This work is not one of the core competencies of the company and was to be placed with an experienced partner who would comply with the operator's time, cost and quality objectives.
The company had faith in the capabilities of IndustrieHansa which was one of the main reasons why it chose to use our specialists.
Solution: Overall construction management was placed in the experienced hands of an IndustrieHansa team which while implementing the project communicated all plans promptly, in full, in detail and in a structured manner to everyone involved internally and externally. Systematic monitoring of project progress was ensured with a high level of transparency and interventions made for control purposes as required. The work involved ranged from defining measures and people responsible for solutions (e.g. problem-solving team) to various levels of escalation (e.g. contractual penalties).
Puncture points
- Overall construction management for paintshop (technology interface)
- Coordination of safety and risk management
- Organization and coordination of operation on the construction site
- Higher-level coordination with assembly sections and deadline coordination
- Monitoring of assembly, process monitoring
- Approval of changes to agreed protective measures
- Higher-level management of areas (staging areas, office, warehouse)
- Monitoring quality and implementation (support for sub-project managers)
- Commissioning
Benefits
The project was completed on time which satisfied another milestone in the customer's defined reference factory. By choosing to work with IndustrieHansa experts, the customer also benefited from a smooth and organized project and can be sure that the high level of flexibility achieved in resource planning will also impact positively on costs beyond this project.